Al-Bayda oilfield is on track to increase production by the end of October
The Arabian Gulf Oil Company (AGOCO) has announced further work to modify the well line (B-56) at Station No (GS1) in Al-Bayda field, to increase production capacity in the field, and it is anticipated that all work will be completed by the end of October.
The company said in a Facebook post, that the work is being conducted at high temperatures، while the pipeline maintenance unit in Al-Bayda field is carrying out work to change the well’s production line, which is approximately 2200 metres long.
Al-Bayda pumps around 7,000 barrels of oil every day.
In mid-September, pipeline tie-in work began at a 60% completion rate, starter in coordination between technical affairs and operations, and with the help of the Department of Transport and the monitoring of the Department of Security, according to the statement.
How to submit an Op-Ed: Libyan Express accepts opinion articles on a wide range of topics. Submissions may be sent to oped@libyanexpress.com. Please include ‘Op-Ed’ in the subject line.
- Libya’s HCS invites applicants for key state roles - December 31, 2023
- UK calls on Iran to prevent escalation in Israel-Hamas conflict - November 05, 2023
- Libyan Interior Minister: Immigrant shelter costs a fortune - November 05, 2023